Unit 3: Standard Field Execution Procedures

Updated: 18 min readBy the Azl technical team

Why write standard procedures and hold points?

Most insulation failures found after handover are not caused by the material itself but by a step that was skipped or rushed: a surface that was never cleaned of cement laitance, a crystalline coat that dried under the midday sun, or a membrane lap whose underside never melted. A standard operating procedure (SOP) turns a good technician's experience into a repeatable list, and it defines inspection hold points: moments after which work may not proceed to the next step until a supervisor or consultant has inspected and signed off.

This unit covers four systems common in rehabilitation projects and new insulation work. Before you start, review Unit 1 on equipment and Unit 2 on safety, because every procedure here assumes the equipment is calibrated and the work permit and protective gear are in place.

Types of control points used in this unit
CodeMeaningWho signsWhat happens if the inspector does not attend
Hold point (H)Mandatory stop until inspection and sign-offSupervisor, then consultantWork may not proceed under any circumstances
Witness point (W)Inspector is notified and may attendSupervisorWork may proceed after the agreed notice period
Records review (R)Review of documents such as material batches and weather readingsQC officerReview is completed before final acceptance
Actual hold points are defined in a project-specific inspection and test plan (ITP).

Substrate acceptance before insulation

  • Surface free of dust, oils, weak old paint and cement laitance
  • Surface roughness matches the data sheet requirement, compared against ICRI concrete surface profile (CSP) chips where needed
  • New concrete has completed the curing period required by the system data sheet
  • Cracks, honeycombing and exposed rebar repaired to the repair specification before starting
  • Falls toward drains are correct with no visible ponding spots
  • Moisture condition suits the system: saturated surface dry (SSD) for crystalline, dry for membranes, foam and polyurea
  • Surface temperature above dew point by the margin the data sheet sets, with the reading recorded
  • Internal corners chamfered or fitted with a cant fillet where the system requires
  • Drains, pipes and penetrations permanently fixed before insulation, not after
  • Material batches recorded, within shelf life and stored within the specified temperature

Printable checklist — use your browser's print command.

Procedure 1: Crack injection with polyurethane or epoxy resins

Injection treats a crack from the inside instead of covering it from the surface. The first decision is not how to inject but what to inject and why. The European standard EN 1504-5 (external source via the Consumer Safety Center) classifies concrete injection products into three categories: F for force-transmitting filling, D for ductile filling, and S for swelling-fitted filling. That classification summarises the difference between epoxy and polyurethane.

When to use polyurethane and when to use epoxy
CriterionPolyurethane resin (PU)Epoxy resin
PurposeStop water ingress and seal the crack flexiblyRebond the crack structurally and transfer forces across it
Crack conditionDamp or actively leakingDry, or damp without pressing water, and stable (dormant)
Expected movementTolerates limited movementUnsuitable for active, moving cracks
Closest EN 1504-5 categoryD or S depending on productF
PrerequisiteKnowing the water sourceStructural engineer's assessment of the cause and the need for structural repair

There are two types of polyurethane. A hydrophobic resin needs only a little water to trigger the reaction and water does not become part of the cured material, so it does not shrink or swell with drying and wetting. A hydrophilic resin absorbs water and forms a highly flexible foam or gel, but it may shrink if its surroundings dry out, as the SealBoss comparison (external source via the Consumer Safety Center) explains. In buried tanks and basements that stay damp, hydrophilic may suit; for elements exposed to wet-dry cycles, hydrophobic is usually preferred. The final call belongs to the data sheet.

RAP-1 states that epoxy injection addresses cracks from about 0.05 mm wide, and that fine cracks (about 0.25 mm and below) need low-viscosity epoxy (500 cps maximum). The Sika method statement (external source via the Consumer Safety Center) notes that slow, low-pressure injection is more effective than rapid, high-pressure injection.

Drilling geometry: angle and spacing

The common method is injection through angled drill-in packers rather than surface ports alone. The Sika method statement and the De Neef TB-0055 bulletin (external source via the Consumer Safety Center) call for drilling at 45 degrees, alternating sides of the crack, so that each hole intersects the crack near mid-depth of the element. Packer spacing is about half the element thickness (d/2), and holes are offset from the crack by about half the thickness as well; a 30 cm wall is drilled about 15 cm from the crack. The narrower the crack, the closer the packers.

offset from crack ≈ d / 2 , packer spacing ≈ d / 2

d is the thickness of the concrete element. Example: a 30 cm wall → offset and spacing of about 15 cm, confirmed on site by checking that every hole actually intersects the crack (flush water emerging from the crack proves it).

  1. 1

    Diagnose and select the material

    Identify the crack type (hairline, shrinkage, movement, structural) and the water condition (dry, damp, active leak). Choose PU or epoxy using the table above and record the decision. Hold point H1: consultant approval of the material, plus the structural engineer's approval if the crack is in a load-bearing element.

  2. 2

    Clean and mark the crack

    Clean the surface on both sides of the crack and mark its path and alternating packer positions. For epoxy, seal the crack face with a temporary surface seal after fitting the ports so resin does not escape.

  3. 3

    Drill and fit packers

    Drill about 1 mm larger than the packer diameter, as Sika specifies, at 45 degrees to roughly mid-depth. Blow the dust out of the hole, insert the packer and tighten it.

  4. 4

    Flush with water (for polyurethane)

    Flush the crack with water through the packers until the water runs clean; this removes dust and confirms each hole connects to the crack. Epoxy work is generally not water-flushed, and Sika notes that oil contamination needs appropriate pre-flushing. Witness point W1: confirm every packer connects to the crack.

  5. 5

    Inject from the bottom up

    On a vertical crack start at the lowest packer; on a horizontal crack start at the narrowest point or one end. Continue until resin appears at the adjacent packer, then move to it. The De Neef bulletin notes injection pressure may range from about 200 to 2,500 psi depending on crack width, concrete thickness and condition, so start low and increase gradually.

  6. 6

    Monitor pressure and consumption

    Record for each packer: pressure, quantity, injection time, and resin emerging at the next packer. A sudden pressure rise with no flow may mean a blockage; a sudden drop may mean resin escaping into a void or out of the element. Carry out secondary injection within pot life if needed.

  7. 7

    Remove packers and patch

    After full cure per the data sheet, remove the packers or cut them flush, fill the holes with a suitable repair mortar, and grind off the surface seal. Hold point H2: visual check for absence of seepage and, where the engineer requires, a core or non-destructive test as RAP-1 suggests.

Procedure 2: Crystalline slurry system

Crystalline materials react chemically with moisture in the concrete and cement hydration by-products to form crystals that block pores and hairline cracks. Water is therefore not the enemy here but a condition for success. The chemistry is covered on the crystalline waterproofing page; the figures below come from the Xypex Concentrate data sheet (external source via the Consumer Safety Center) and the Xypex coating installation guide (external source via the Consumer Safety Center) as an example of one well-known product, and may differ for others.

Typical values from one crystalline product data sheet (Xypex Concentrate), for guidance
ItemValue in the data sheetField note
Surface profileCSP-3 per ICRI guidelinesSmooth surfaces are sand-blasted, water-blasted or acid-etched to open the pores
Surface conditionSaturated surface dry (SSD)No glistening free water on the surface at the time of application
Mix ratio, brush5 parts powder : 2 parts waterMix only what will be used before it starts to stiffen
Mix ratio, spray5 parts powder : 3 parts waterPer the approved spray equipment
Coverage per coat0.65–0.8 kg/m²A single heavy coat of about 1.0 kg/m² in some applications
ThicknessJust under 1.25 mmThicker coats may cause curing problems, especially in warm weather
Second coatWithin 48 hours while still greenAfter initial set, with light misting between coats
Moist curingMist spray 3 times a day for 2–3 daysMore frequent spraying may be needed in hot, arid conditions
Tanks and basins3 days of curing, then 12 days before fillingAbout 15 days in total before the water test
Minimum temperatureDo not apply below 4°CIn Saudi Arabia the problem is usually high heat, not low
Values are taken from the named manufacturer's documents and must be replaced with those of your approved product.
  1. 1

    Surface preparation

    Remove laitance, paint and oil, and open the pores to the required profile. Treat honeycombing and cracks wider than hairline by chasing them to a U-shaped groove and filling with the dedicated product (Dry-Pac or equivalent). Hold point H1: acceptance of surface profile and cleanliness.

  2. 2

    Saturate to SSD

    Spray the surface with clean water until saturated (preferably from the previous night for old, dry concrete), then remove free water immediately before application. The surface should look dark and damp with no sheen.

  3. 3

    Mix

    Mix powder and water at the ratio in the data sheet with a low-speed mixer, and never add water later to re-temper a mix that has started to stiffen.

  4. 4

    Apply by brush or spray

    Use a semi-stiff nylon brush, a push broom for large horizontal areas, or dedicated spray equipment. Work the material into the pores and keep the thickness even. Check consumption by dividing the quantity used by the area covered.

  5. 5

    Second coat

    Where the specification calls for two coats, apply the second after the initial set of the first while it is still green, with light misting in between. Witness point W1: review the consumption log against the required rate.

  6. 6

    Moist curing and protection

    Start mist spraying as soon as the coat can take it without washing off, and repeat as the data sheet requires. Protect the surface from direct sun and drying wind with wet hessian or shading, and do not cover it with a fully impermeable material without the manufacturer's approval. Hold point H2: sign the daily curing log before any backfilling, covering or filling.

Procedure 3: Torch-applied bituminous membranes

A modified bituminous membrane (SBS or APP) is bonded by melting its bitumen underside with a torch onto a primed surface. Success depends on three things: a dry, clean substrate, lap width, and melt quality. The material itself is covered in the bituminous membrane guide, and hot-works safety requirements in the safety unit.

Comparison of lap and detail values in three published references
ItemSika torch-on membrane guideInsuflex SBS data sheetCanadian Roofing Contractors Association (CRCA)
Side lap6 cm minimum8–10 cm75 mm minimum
End lap10 cm minimum12–15 cm150 mm minimum
End-lap staggerAt least 1 m between adjacent end lapsNot statedSpecified offsets between base and cap sheets
PrimerPer substrate type and product data sheet0.2–0.3 L/m² depending on porosityNot stated in this section
Upstand10 cm onto the horizontal in detailsNot stated200 mm minimum above the roof surface
Note the variation between sources: the binding reference is the data sheet of the supplied membrane and the project specification, and the smallest figure must not be borrowed from another source.
  1. 1

    Substrate acceptance

    A dry, clean surface free of grease, dust and loose particles, with correct falls to drains. Form a cant fillet where the deck meets the wall so the membrane does not bend at a sharp angle. Hold point H1: acceptance of substrate, falls and details.

  2. 2

    Primer

    Apply bituminous primer by brush, roller or spray at the data sheet rate (Insuflex example: 0.2–0.3 L/m²) and let it dry fully before torching; wet primer is flammable and weakens adhesion. Witness point W1: check primer dryness.

  3. 3

    Alignment and dry lay

    Lay the rolls out dry first and align them with a chalk line, starting at the lowest point (the drain) and working upward so each roll overlaps the one below in the direction of water flow. Then re-roll them ready for torching.

  4. 4

    Torching technique

    Direct the flame at the junction between the substrate and the underside of the roll, melting the backing film until it starts to flow, then push the roll forward. A continuous bead of molten bitumen should appear at the lap edge; the Sika guide mentions about 1 cm, while the CRCA manual limits bleed-out at cap sheet side laps to about 6 mm. No bead means under-melting; heavy bleed-out means excessive heat that can damage the reinforcement.

  5. 5

    End laps

    Cut the membrane corner at the end lap at 45 degrees (the Sika guide describes a triangle of 10 cm per side), and heat the mineral surface of the underlying roll thoroughly until the granules sink in. Stagger end laps as shown in the table.

  6. 6

    Sealing the laps

    Press the lap while hot with a seam roller. The Sika guide warns against filling or scraping laps with a trowel or spatula because it can damage the membrane reinforcement, so use a hot trowel only where your product data sheet calls for it to finish the edge. Hold point H2: probe every lap with the tip of a cold trowel under light pull to find unbonded areas.

  7. 7

    Upstands and details

    Install reinforcing strips at corners, drains and pipes before the main layer, turn the membrane up walls to the height in the specification, and secure the top edge with a metal termination bar and sealant or in a wall chase.

  8. 8

    Water test and protection

    Once complete, carry out the water test per the checklist below, then install the protection layer or thermal insulation on top according to the roof design. For the full layer sequence see the roof insulation guide.

Procedure 4: Spray foam with topcoat, and polyurea

Both systems rely on heated plural-component spray equipment (proportioners), whose setup we covered in the equipment unit. Here we give the short field sequence; for more on the materials see the spray polyurethane foam guide and the polyurea guide for Saudi Arabia.

  1. 1

    Measure conditions

    Record air and surface temperature, relative humidity and dew point before starting and every two hours. Many data sheets require the surface to be at least about 3°C (5°F) above the dew point. Hold point H1: sign the weather log and confirm the surface is dry.

  2. 2

    Test spray

    Spray a sample on a board off the roof to check reactivity, density, colour and cell structure of the foam, or cure time and appearance for polyurea, before spraying the work.

  3. 3

    Primer where required

    Apply the approved primer to concrete or metal within its recoat window. On concrete the primer also helps reduce bubbles from gases escaping the pores.

  4. 4

    Spray foam in passes

    The SPFA technical bulletin states a minimum single pass on roofs of about 13 mm (half an inch) to reduce blistering, that the maximum is set by the manufacturer, and that 15–30 minutes should be allowed between passes to dissipate heat. Witness point W1: measure thickness with a probe at an agreed frequency.

  5. 5

    Topcoat the foam

    Exposed foam degrades under ultraviolet light, so it is covered with a topcoat (acrylic, polyurethane or polyurea) within the time the manufacturer allows and at the required dry film thickness. Hold point H2: measure the topcoat dry film thickness before acceptance.

  6. 6

    Spray polyurea

    Spray in cross-hatched passes to reach the specified thickness, respecting the recoat window; in a case documented by KTA the window was 16 hours and the data sheet required sanding beyond it. Aromatic polyurea needs a UV-resistant topcoat if exposed. Hold point H3: visual check for pinholes, and an adhesion test where the specification requires.

Water testing and final acceptance

Water testing of horizontal surfaces usually follows ASTM D5957, a guide that leaves water depth and duration to the project specification. One published example is an American Hydrotech technical bulletin requiring flooding the membrane with at least two inches (about 50 mm) of water for 24 to 48 hours (external source via the Consumer Safety Center), followed by inspection of the slab underside. Confirm structurally that the slab can carry the water load before testing (every 10 cm of water weighs about 100 kg/m²).

Water test and final acceptance

  • The last layer has completed the cure time required by the data sheet before flooding
  • Drains plugged with removable stoppers and temporary dams at edges and joints
  • Water depth and duration match the project specification and are documented with photos and times
  • Soffit, walls and areas around drains and pipes inspected at the start and end of the test
  • Water level recorded at the start and end to distinguish evaporation from leakage
  • Any seepage is marked and repaired, then the affected area is retested
  • Water drained after the test without damaging the membrane, and the protection layer installed promptly
  • Handover file compiled with material batches, weather logs, thicknesses and test results
  • Final acceptance report signed by the supervisor, consultant and owner

Printable checklist — use your browser's print command.

A complete acceptance file is the basis of any warranty: at Azl a written warranty is issued whose duration depends on the insulation type and surface condition, detailed in the warranty policy. If seepage appears during the test, go to Unit 4: the troubleshooting guide to diagnose the cause before patching.

Frequently asked questions

Can an actively leaking crack be injected with epoxy?

Usually not. Structural epoxy needs a crack that is dry, or damp without pressing water, to bond to the crack faces. A crack with flowing water is first treated with a polyurethane resin that reacts with water and stops the leak; a structural engineer then decides whether it needs structural rebonding afterwards. Some products tolerate moisture, so check the specific product data sheet.

How do I know the correct spacing between injection packers?

The rule published by manufacturers such as Sika and De Neef is spacing of about half the element thickness, drilling at 45 degrees on alternating sides so each hole meets the crack near mid-depth. Narrow cracks need closer packers. The practical check is flush water or resin emerging from the adjacent packer; if it does not, add a packer in between.

Why must the surface be saturated before applying crystalline slurry?

Because the crystalline reaction needs water to migrate into the pores and react with cement compounds. A dry surface sucks water out of the mix so the coat dries before it reacts and may crack or dust. The required state is saturated surface dry: the concrete is saturated internally with no glistening free water on the face at the time of application.

What is the correct lap for bituminous membrane joints?

It depends on the manufacturer and reference. The Sika guide gives a minimum of 6 cm side and 10 cm end laps, another data sheet gives 8–10 cm and 12–15 cm, and the Canadian roofing manual gives 75 mm and 150 mm. The binding values are those of the supplied membrane's data sheet and the project specification; never borrow the smallest figure from another source to save material.

How long should a roof water test last after waterproofing?

ASTM D5957 leaves depth and duration to the project specification. One published example is flooding the membrane with about 50 mm of water for 24 to 48 hours and then inspecting the underside. Before that, confirm the material has completed its cure time and the slab can carry the water load, and record the water level at the start and end.

What is an inspection hold point, and does it delay the project?

A hold point is a moment at which work may not move to the next step until the supervisor or consultant has inspected and signed, such as substrate acceptance before priming. It may add hours to the schedule, but it saves days of rework later, because discovering an unprepared surface after it is covered means removing the whole system. Hold points are set in advance in the inspection and test plan.

Technical or training enquiry

For technicians and engineers: ask about an application, a machine or a step in this unit.

Nothing is stored on this website; your message opens in WhatsApp for you to send to 0544027180. Privacy policy

References and sources

  1. Method Statement: Sika Crack Injection, structural — Sika UK · gbr.sika.com
  2. TB-0055 Standard Application Procedures for Sealing Leaking Cracks or Joints with Grouts — GCP Applied Technologies (De Neef) · gcpat.com
  3. RAP-1: Structural Crack Repair by Epoxy Injection — American Concrete Institute · concrete.org
  4. BS EN 1504-5:2013 Concrete injection — NBS / BSI · thenbs.com
  5. Hydrophobic versus Hydrophilic Polyurethanes — SealBoss Corp. · sealboss.com
  6. Xypex Concentrate Product Data Sheet — Xypex Chemical Corporation · xypex.com
  7. Concrete Coating Installation and Procedures — Xypex Chemical Corporation · xypex.com
  8. Application Guide: Bituminous Torch-on Membranes — Sika South Africa · zaf.sika.com
  9. Insuflex SBS Technical Data Sheet — Insumat · insumat.com
  10. 5.2.2 Application of Membrane — Canadian Roofing Contractors Association · roofingcanada.com
  11. Technical Bulletin: Flood Testing — American Hydrotech · hydrotechusa.com
  12. TechTip I2: Exothermic Temperatures in SPF — Spray Polyurethane Foam Alliance · upcfoam.com

External links pass through Azl's Consumer Safety Center for checking before leading to other organisations' websites. Citing them does not imply they endorse Azl. Technical values are typical and vary by product; the final reference is the approved product's datasheet and the project design. Editorial policy