Unit 1: Mechanical Equipment and Instruments in Insulation Work

Updated: 19 min readBy the Azl technical team

This unit covers the equipment that insulation technicians and site engineers handle every day: the high-pressure proportioners used for polyurea coating and spray polyurethane foam, spray guns, surface preparation machines and quality-control instruments. Most failed coatings on site are not caused by the material itself but by an out-of-adjustment machine, a poorly prepared surface or a test that was not done on time.

High-Pressure Plural-Component Proportioners

The plural-component proportioner is the heart of any polyurea or foam spray rig. Feed pumps draw component A (the isocyanate, often called ISO) and component B (the resin or polyol) from their drums. Two synchronized proportioning pumps then push both components at a fixed volume ratio through primary heaters that bring each one to its set temperature, and each component travels through its own heated hose until the two meet for the first time inside the gun's mix chamber. No mixing happens inside the machine or the hoses, so any crossover between the two lines means a reaction in a place where none should occur.

Most common systems run at a 1:1 ratio by volume. Graco's brochure on fast-set plural-component equipment states that standard Reactor models such as the H-25, E-30, E-XP2 and H-XP2 are fixed 1:1 machines, with the option of changing the A or B pump for other fixed ratios. In practice the machine delivers the same volume of each component, so any difference in viscosity or temperature, or a partial blockage in one line, immediately upsets the ratio.

Electric versus hydraulic

Electric units drive both pumps with a motor and gearbox, so they are lighter and easier to transport. Hydraulic units drive the pumps with a hydraulic cylinder, giving higher output and better tolerance of continuous duty, but they require maintenance of the hydraulic oil and its filters. The more important criterion is the working pressure the material requires, which is why manufacturers separate models intended for foam from models intended for polyurea and coatings.

Examples of Graco Reactor models and their intended use per manufacturer documentation (for illustration, not a recommendation)
ModelDriveDesigned forMax fluid working pressureMax fluid temperature
Reactor 2 E-30ElectricSpray polyurethane foam2000 psi (approx. 140 bar)190°F (88°C)
Reactor 2 E-XP2ElectricPolyurea coatings3500 psi (approx. 241 bar)190°F (88°C)
Reactor H-25HydraulicFoam and some polyurea coatings2000 psi (approx. 138 bar)190°F (88°C)
Reactor 2 H-XP2HydraulicPolyurea and protective coatings3500 psi (approx. 241 bar)190°F (88°C)
Reactor 3 H-XP3HydraulicHigh-output polyurea3500 psi (approx. 241 bar)180°F (82°C)
These are machine maximums, not operating settings. Actual pressure and temperature settings come from the material's technical data sheet and the manufacturer's manual, and figures can differ between manual editions.

Heated hoses

Heated hoses keep both components at temperature all the way to the gun, because temperature controls viscosity and viscosity controls mixing quality. The bundle contains the A and B lines, an air line and a temperature sensor near its end. The Reactor 2 E-30 and E-XP2 manual states that the maximum heated hose temperature is 10°F (5°C) above the highest A and B setpoint, or 180°F (82°C). Each model also specifies a maximum permissible heated hose length in its manual.

Recommended settings

There are no universal settings that suit every material. Spray pressure, primary heater temperature and hose temperature are set per the manufacturer's manual and per the material's technical data sheet, which usually specifies a temperature range for each component and a minimum spray pressure; cross-check these against our guide to technical data sheets. Set temperature first and let it stabilize, then pressure, then spray a sample onto a test panel. Modern units support a pressure imbalance alarm between the two lines, and the Reactor 2 manual lets you enable this alarm and set the allowable deviation. Never disable it to speed up work; it is the first sign of a blockage or an off-ratio condition.

Ratio check procedure

Some models fitted with flow meters can monitor the ratio electronically and trigger an alarm at a set percentage, as the Reactor 2 manual describes for Elite models. A manual check is carried out according to the manufacturer's manual using the ratio check device for that machine. The general logic is as follows:

  1. 1

    Prepare

    Wear full PPE, bring the machine to its normal operating temperature and pressure, and let the readings stabilize for several minutes.

  2. 2

    Separate the components

    Use the manufacturer-approved ratio check device or sampling valves so that each component is dispensed separately without mixing. Never disassemble anything under pressure.

  3. 3

    Take samples

    Collect A and B into clean, labeled, pre-weighed containers over the same dispense time and at the same pressure.

  4. 4

    Calculate

    Weigh both samples and convert weight to volume by dividing by each component's specific gravity from the data sheet. Compare the volume ratio with the required ratio and the tolerance stated on the data sheet.

  5. 5

    Act on the result

    If the ratio is outside tolerance, stop spraying and check the inlet strainers, feed pumps, temperatures and the pressure of each line. Do not resume until the cause is corrected and the check is repeated.

Preventive maintenance and machine safety

  • Check the level and condition of the ISO pump lubricant daily as the Reactor 2 manual requires, and keep the component A wet-cup reservoir filled with Throat Seal Liquid (TSL) as the pump type requires.
  • Inspect the fluid inlet strainer daily; a clogged strainer is one of the most common causes of off-ratio spraying and pump starvation.
  • Grease the circulation valves weekly as the manual specifies.
  • Store isocyanate in a sealed container with a desiccant dryer in the vent or under a nitrogen blanket, and never in an open container; moisture crystallizes the material and damages pump seals.
  • At the end of the day follow the component A pump parking procedure in the manual, and relieve pressure before any disassembly or cleaning.
  • Only a qualified technician may open the electrical enclosure, and never point the gun at anyone; a high-pressure injection injury under the skin is a surgical emergency.

Plural-Component Spray Guns

Each component enters through a small port on the side of the mix chamber, the two streams collide at high velocity and leave as a mixed spray. When the trigger is released the chamber must be cleared of mixed material immediately, or it will cure inside.

Two Graco gun examples per manufacturer manuals
ItemFusion APProbler P2
Purge principleAir: when de-triggered the mix chamber moves forward to shut off fluid, and the impingement ports open to the air chamber so purge air flows through the mix chamber nozzleWhen de-triggered the mix chamber returns to its original position, shutting off material flow, and purge air is directed through the chamber
Max fluid pressure3500 psi (245 bar)3500 psi (241 bar)
Max fluid temperature200°F (94°C)Not stated in the manual we reviewed
Air inlet pressure80–130 psi (5.6–9.0 bar)90–110 psi (6.2–7.6 bar)
MaterialsFast-setting plural-component materialsNon-flammable foam and polyurea
Sources: Graco manual 309550 for the Fusion AP and manual 313213 for the Probler P2. Always consult the edition that matches your gun.

Mix chamber components and O-rings

  • Mix chamber: its size sets flow rate and pattern. The Fusion AP offers round-pattern sizes from AR2020 to AR8686 and flat-pattern sizes from AF2020 to AF5252. Size selection follows the machine's output and the material's data sheet.
  • Side seals: spring-loaded cartridges with O-rings that stop material leaking between the fluid housing and the mix chamber. Scratching a seal face during cleaning causes leakage and crossover.
  • Check valves: one valve per line prevents one component from backing into the other's line. A blocked or damaged check valve leads to a reaction inside the manifold.
  • Air cap and purge system: needs clean, dry air at the pressure the manual specifies; wet or oil-contaminated air contaminates the coating and speeds up chamber clogging.
  • O-rings: must be of the material the manufacturer specifies, replaced at any sign of swelling or cracking, and never substituted with generic rings.

Daily cleaning and lubrication to prevent crossover and clogging

Crossover is when one component reaches the other component's side inside the gun, where they react and cure in the passages. The Fusion AP manual calls for greasing the gun daily to prevent two-component curing and keep fluid passages clean, dispensing grease until a grease mist sprays from the mix chamber nozzle, with a maximum of two shots, then checking that the air valve shuts off. The Probler P2 manual calls for injecting one full pump of white lithium grease into the zerk fitting at nightly shutdown. A typical sequence:

  1. 1

    Close the fluid valves

    Close the A and B valves on the gun and relieve pressure following the pressure relief procedure in the machine manual.

  2. 2

    Clean the front

    Clean the gun face and air cap with a solvent approved by the material supplier, without metal tools that scratch surfaces.

  3. 3

    Lubricate

    Grease the gun by the method and quantity the model's manual specifies, without over-greasing.

  4. 4

    Check seals and ports

    When the chamber is removed, clear the impingement ports with the drill bit sizes listed in the manual's table, and clean the side blocks without scratching the seals.

  5. 5

    Store

    Store the gun clean with the valves closed, and do not leave it soaking in solvent unless the manual allows it.

Surface Preparation Equipment

Adhesion starts at the surface. ICRI Technical Guideline 310.2R uses the concrete surface profile (CSP) scale from 1 (nearly flat) to 10 (very rough), with reference chips for visual and tactile comparison. Each coating or membrane data sheet usually specifies the required profile, and the technician must choose the machine that achieves it without weakening the concrete's surface layer.

CSP ranges produced by preparation methods per Table 7.2 of ICRI 310.2R-2013
Preparation methodResulting CSP range
GrindingCSP 1–2
ShotblastingCSP 2–9
Abrasive blastingCSP 1–9
High- and ultra-high-pressure water jettingCSP 1–9
The actual result depends on the machine, its settings and the concrete strength; always compare against the CSP reference chips.

Diamond grinders

A diamond grinder removes laitance and thin coatings with diamond segments on a rotating head, leaving a relatively smooth surface suited to thin systems such as epoxy. Settings (diamond type, grit and speed) are per the manufacturer's manual and the concrete type. Maintenance: check segment wear, the dust shroud and the power cable. Safety: guard always in place, eye and hearing protection.

Shot blasting machines

The machine throws steel shot with a spinning wheel, recovers it and sends the dust to the collector, producing a coarser, uniform profile suited to thicker coatings. Shot size and travel speed control the result and are set per the manufacturer's manual after a trial on a small area. Maintenance: check liners, blades, wheel and collector filters. Safety: never lift the machine while the wheel is spinning.

Sandblasting and abrasive blasting

Compressed air propels an abrasive through a nozzle; the method suits irregular and metal surfaces. It needs a compressor sized to the nozzle, a dryer and filters for moisture and oil, and an air-fed blast helmet. Abrasive type and air pressure are set per the manufacturer's manual and the project specification. Maintenance: check nozzle, hose and coupling wear, drain the compressor, and test the remote control (deadman) valve. Safety: the deadman control must always work, hoses must be secured with whip checks, and dust must be controlled with bystanders protected.

High-pressure water jetting

Pressurized water removes old coatings and weak concrete without dust and is preferred where dust or sparks are prohibited. The UK Water Jetting Association (WJA), based on NACE definitions, classifies the ranges as follows:

Water jetting pressure bands per WJA guidance
CategoryPressure range
Low-pressure water cleaningUp to 207 bar (3,000 psi)
High-pressure water cleaningAbove 207 bar up to 680 bar (10,000 psi)
High-pressure water jettingAbove 680 bar up to 1,700 bar (25,000 psi)
Ultra-high-pressure water jettingAbove 1,700 bar
The pressure required for each job is set by the equipment manual and the project specification, and high and ultra-high pressure work requires operators trained specifically for it.

After water jetting the surface must dry and its moisture must be measured before coating. Maintenance: inspect hoses, couplings, nozzles and water filters. Safety: water jet injuries may look minor yet be deep, so never operate without specific training, full protection and a deadman control.

Dust extraction

Grinding and blasting concrete releases respirable crystalline silica. Table 1 of OSHA 29 CFR 1926.1153 (external source via the Consumer Safety Center) gives two options for walk-behind floor grinders and milling machines: continuous water feed to the cutting surface, or a manufacturer-recommended dust collection system with 99% or greater efficiency and a filter-cleaning mechanism, plus a HEPA-filtered vacuum between passes for indoor work. Never rely on dry sweeping.

QA/QC and Coating Inspection Tools

Concrete moisture meters

Electronic surface moisture meters are useful for quick comparative surveys, but they do not replace standard methods. The first method is ASTM F2170, using in-situ relative humidity probes: the hole is drilled to 40% of slab thickness for a slab drying from one side (on grade) and 20% for a slab drying from both sides (suspended), the hole equilibrates for 24 hours before reading, the space is held at service conditions for at least 48 hours beforehand, and three probes are used for the first 1,000 ft² (about 100 m²) plus one for each additional 1,000 ft². The second method is ASTM F1869, the calcium chloride test: a dish of anhydrous calcium chloride is sealed onto bare concrete for 60 to 72 hours, and its weight gain gives the emission rate in pounds per 1,000 ft² per 24 hours. It measures the surface only and is influenced by site conditions during the test, as this comparison (external source via the Consumer Safety Center) explains.

Holiday and spark testers

These instruments detect pinholes, voids and cracks in an electrically insulating coating. On concrete the reference is ASTM D4787 for continuity verification of liquid or sheet linings applied to concrete, which uses a high-voltage spark tester with pulsed or continuous DC and may require a conductive underlayment (for example a carbon or graphite-filled primer) because concrete conductivity varies with moisture and reinforcement; it applies to newly applied linings only. On conductive substrates such as steel the reference is NACE SP0188 (now within AMPP standards), which describes two instruments: the low-voltage wet sponge and the high-voltage spark tester. The wet sponge typically operates at 67.5 to 90 volts for coatings under 500 microns, and high-voltage testing is used for thicker films, as this technical explainer (external source via the Consumer Safety Center) describes. The correct voltage is set per the specification and the instrument manual; excessive voltage can puncture a sound coating. Never use a high-voltage tester in a flammable atmosphere.

Dry film thickness (DFT) gauges

On steel, magnetic or eddy-current gauges are used according to ASTM D7091 (external source via the Consumer Safety Center), which covers verifying gauge accuracy and adjustment and does not apply to coatings that deform under the probe load. On concrete, wood and other non-metallic substrates the ultrasonic gauge is used according to ASTM D6132, which states a measuring range of 8 micrometers to 7.60 mm; in multi-layer systems the instrument may only detect the interface between the two most acoustically different materials. Verify the gauge on reference shims before every shift.

Pull-off adhesion tester

A dolly is glued to the coating with a suitable adhesive, then the tester pulls it perpendicularly until it detaches, and the load and failure mode are recorded: within the concrete, between coating and substrate, within the coating, or in the glue. On concrete the reference is ASTM D7234, a destructive test that may need spot repair afterwards, with failure occurring along the weakest plane in the system. On metals the reference is ASTM D4541 (external source via the Consumer Safety Center), which warns against comparing results from different instrument types. The acceptance value comes from the specification or data sheet, not from the instrument. Maintenance: keep dollies and their faces clean and calibrate the tester periodically per the manufacturer.

Summary of inspection tools and reference standards
ToolWhat it measuresReference standardWhen it is used
RH probeMoisture inside the slabASTM F2170Before moisture-sensitive coatings
Calcium chloride testSurface vapor emission rateASTM F1869When the data sheet requires it
Spark tester on concreteLining continuityASTM D4787After curing of tank and basin linings
Holiday tester on steelCoating continuityNACE SP0188Coatings on metal surfaces
Magnetic DFT gaugeCoating thickness on metalASTM D7091During and after application
Ultrasonic DFT gaugeCoating thickness on concreteASTM D6132During and after application
Pull-off testerAdhesion strength and failure modeASTM D7234 / D4541Trial areas and final acceptance

Preventive Maintenance Schedule

A general framework to be adapted to each model's manual; where they differ, the manufacturer's manual governs.

Daily, weekly and monthly preventive maintenance tasks
EquipmentDailyWeeklyMonthly
ProportionerCheck ISO pump lubricant and TSL reservoir, inspect inlet strainer, review pressure and temperature alarms, park pump A and relieve pressure at shutdownGrease circulation valves, check for leaks around pumps, check drum desiccant dryersReview fault log, electrical connections checked by a qualified technician, hydraulic oil and filter service on hydraulic units per manual
Heated hosesVisual check of outer insulation, cracks and sharp bends; confirm temperature sensor readingCheck couplings and leaks at jointsCheck heating element resistance and connections per manual, inspect the whip hose
Spray gunsClean face and air cap, grease per manual, inspect side sealsClean impingement ports and screens, inspect check valvesReplace worn O-rings and seals, review spare parts stock
Compressor and air dryerDrain water from tank and filters, check oil level, confirm air is dryClean intake filter, check belts and connectionsReplace filter elements per running hours, test safety valve
Grinders and prep equipmentCheck diamond segments, guard and cable; empty dust collectorCheck dust collector filters and hose, inspect shot blaster linersCheck bearings, carbon brushes and connections; review filter running hours

Field Checklists

Pre-spray checklist

  • Work permit is valid and the safety plan has been reviewed with the crew
  • Material technical data sheet and safety data sheet (SDS) are available on site
  • Surface prepared to the required profile and free of dust and oil
  • Surface moisture measured, recorded and within the data sheet limit
  • Surface and air temperature, relative humidity and dew point measured and recorded
  • Primer applied and within its specified recoat window
  • Component temperatures and spray pressure set per the data sheet and manufacturer's manual
  • Test spray on a sample panel showed uniform color and normal reaction
  • Adjacent surfaces, windows and equipment masked against overspray
  • Spray zone isolated and marked, with nobody present without PPE
  • Ventilation in place for indoor or semi-enclosed work
  • Batch and drum number record form ready

Printable checklist — use your browser's print command.

Equipment pre-start inspection

  • Power supply matches machine voltage and is earthed; cables intact
  • ISO pump lubricant level and TSL reservoir OK
  • Inlet strainers clean and feed pumps working
  • Drum desiccant dryers fitted and desiccant in good condition
  • Heated hoses free of cracks and sharp bends; temperature sensor reading
  • Pressure imbalance alarm enabled
  • Gun clean and greased; seals and screens in good condition
  • Gun A and B valves working and safety lock functional
  • Compressor running; air clean, dry and within the gun manual's pressure range
  • Breathing air supply separate and inspected, if used
  • Fire extinguisher, first aid kit and eyewash station available
  • QA/QC instruments calibrated and batteries charged

Printable checklist — use your browser's print command.

Once you have mastered the equipment, move on to Unit 2 on occupational safety and confined space procedures, then to the field standard operating procedures. To understand the materials that pass through this equipment, see the pages on polyurea and polyurethane foam.

Frequently asked questions

What is the practical difference between an electric and a hydraulic proportioner?

An electric unit drives the pumps with a motor and gearbox, so it is lighter, easier to transport and suits medium-size jobs. A hydraulic unit drives the pumps with hydraulic oil, giving higher output and better tolerance of continuous duty, but it needs oil and filter maintenance. More important than the drive type is that the model is designed for the material's pressure: common foam models top out around 2000 psi and polyurea models around 3500 psi per manufacturer manuals.

Why are materials and hoses heated when spraying polyurea and foam?

Heat lowers the viscosity of both components, and mixing happens by impingement inside a small chamber in the gun. If the material is too viscous it will not mix well, producing a non-uniform or tacky layer. Primary heaters raise the material to its setpoint and the heated hose only maintains it. Setpoints come from the material's data sheet, and hose limits come from the machine manual.

How can I tell during work that the 1:1 ratio is off?

Field signs include color changes, tacky or brittle patches, a change in reaction time and repeated pressure imbalance alarms between the two lines. If any appear, stop spraying, check the inlet strainers, feed pumps and temperatures, then run a ratio check with the manufacturer's device: collect two separate samples, weigh them, convert them to volume using specific gravity and compare against the tolerance on the data sheet.

Is an electronic surface moisture meter enough before applying polyurea?

It is useful for a quick survey and for locating the wettest areas, but it does not replace the method the material's data sheet requires. Many manufacturers specify a value using in-situ probes to ASTM F2170 or the calcium chloride method to ASTM F1869. If the data sheet does not name a method, consult the supplier before coating, and record readings and their locations in the project log.

What is the difference between wet sponge holiday testing and spark testing?

The wet sponge is a low-voltage instrument, typically 67.5 to 90 volts, suited to thin coatings under about 500 microns on conductive substrates. The spark tester is high-voltage and suits thicker films and linings on concrete tested to ASTM D4787. The correct voltage depends on coating thickness, the specification and the instrument manual, and excessive voltage can damage a sound coating.

How often should a spray gun be greased and cleaned?

The Fusion AP manual recommends greasing the gun daily to prevent components curing in the passages, and the Probler P2 manual calls for greasing at nightly shutdown. In practice the technician cleans the face and air cap and greases at the end of each day, and clears the impingement ports and screens and inspects the check valves weekly or whenever signs of clogging or crossover appear.

Technical or training enquiry

For technicians and engineers: ask about an application, a machine or a step in this unit.

Nothing is stored on this website; your message opens in WhatsApp for you to send to 0544027180. Privacy policy

References and sources

  1. Reactor 2 E-30 and E-XP2 Integrated Proportioning System, Operation Manual 333023 — Graco · graco.com
  2. Fast-Set Plural-Component Equipment for Foam and Coatings Applications — Graco · graco.com
  3. Reactor 3 Hydraulic Proportioning Systems — Graco · graco.com
  4. Fusion AP Spray Gun, Instructions-Parts 309550 — Graco · graco.com
  5. Probler P2 Dispense Gun, Manual 313213 — Graco · graco.com
  6. ICRI Technical Guideline No. 310.2R-2013 (Concrete Surface Profile) — International Concrete Repair Institute · icri.org
  7. WJA issues clear guidance on water jetting pressures — Water Jetting Association · waterjetting.org.uk
  8. How to Measure Concrete RH in Compliance with ASTM F2170 — DeFelsko · defelsko.com
  9. ASTM D4787 Continuity Verification of Liquid or Sheet Linings Applied to Concrete Substrates — ASTM International · store.astm.org
  10. SP0188 Discontinuity (Holiday) Testing of New Protective Coatings on Conductive Substrates — AMPP (NACE) · store.ampp.org
  11. ASTM D6132 Nondestructive Measurement of Dry Film Thickness Using an Ultrasonic Coating Thickness Gage — ASTM International · store.astm.org
  12. ASTM D7234 Pull-Off Adhesion Strength of Coatings on Concrete — ASTM International · store.astm.org

External links pass through Azl's Consumer Safety Center for checking before leading to other organisations' websites. Citing them does not imply they endorse Azl. Technical values are typical and vary by product; the final reference is the approved product's datasheet and the project design. Editorial policy