Waterproofing Foundations Before Backfilling: Steps From Formwork Removal to the First Soil Layer

Updated: 8 min readBy the Azl technical teamConcrete & foundation treatment

Repairing a crack in an underground water tank wall before applying the internal lining
Repairing a crack in an underground water tank wall before applying the internal lining — Illustrative image

Between pouring the concrete and backfilling the excavation there is a short window that never comes back. Once soil closes over the footings and tie beams, nobody sees those surfaces again without an expensive dig. That is why waterproofing foundations before backfilling is not a cosmetic line in the contract. It is the last chance to protect reinforced concrete from ground moisture and salts for the whole life of the building.

This article is a site guide for villa owners and supervising engineers: what should happen, in what order, and what to check before you let the loader push soil in. For the full system and pricing, see our foundation insulation service page.

Why must foundations be waterproofed before backfilling?

Concrete is porous, and the soil around it is rarely as dry as it looks. Moisture rises by capillary action and carries dissolved sulphates and chlorides with it. These salts attack the cement paste and, over time, reach the reinforcing steel. In coastal areas and the Eastern Province the problem is worse, which is why we wrote a separate piece on foundation protection in sabkha soil.

The tie beam is the bridge that carries moisture from the soil into the ground-floor walls. If its top face and both sides are not sealed, damp patches and peeling paint appear at the base of the walls within a few years. The problem is hard to cure later because its source is buried.

What are the steps for waterproofing foundations and tie beams before backfill?

  1. 1

    Wait for formwork removal and initial curing

    Never apply waterproofing to green concrete that is still being wet-cured. Follow the curing period set by the engineer, then let the surface dry to the touch.

  2. 2

    Inspect the concrete before covering it

    Look for honeycombing, voids, protruding tie wires and pipe stubs. Any defect covered by waterproofing stays a weak point. Repair honeycombing first, as described in our guide to concrete honeycombing repair.

  3. 3

    Clean the surface and remove protrusions

    Remove timber offcuts, soil and oil, chip off sharp nibs and cut off wires. Coatings do not bond to dust, and membranes get punctured on sharp edges.

  4. 4

    Form a cove at the corners

    The sharp corner between a footing and its neck, or between a tie beam and the blinding, is rounded with a sloping mortar fillet so the waterproofing can run across it without an air gap or tension.

  5. 5

    Apply a primer if the system requires one

    Some systems start with a thinned primer coat that improves adhesion. Follow the product data sheet and do not mix products from different systems without the manufacturer's approval.

  6. 6

    Waterproof every buried face

    That means the sides of the footings, the necks, both sides of the tie beam and its top face. The underside is protected by the blinding concrete and any membrane beneath it, where the design includes one.

  7. 7

    Let the coats dry, then fit protection

    Do not fit protection boards or backfill until the waterproofing has dried as the product data sheet requires. Otherwise it smears or sticks to the soil and peels off.

  8. 8

    Backfill in compacted layers

    Spread clean soil in layers and compact each one, keeping large stones away from the waterproofed surfaces.

Which materials are used to waterproof foundations and tie beams?

The most common choice on Saudi villas is bitumen coating in its various forms, followed by self-adhesive or torch-applied bituminous membranes, and then crystalline systems that react with the concrete itself. Each has a place where it suits best. Full details are on our pages for bitumen coating and bituminous membranes.

Practical comparison of foundation waterproofing materials
MaterialHow it worksWhat to watch on siteExample from a data sheet
Rubberised bitumen emulsionFlexible continuous film over the concreteAt least two coats, with drying time between coatsThe Sika Igolflex AE data sheet lists a minimum of two coats and about 1 mm dry thickness at 1.8 kg/m²
Standard bitumen emulsionMoisture and vapour barrierSuitable where the risk is damp, not water under pressureFosroc lists 0.5–0.7 kg/m² over two coats for Nitoproof 21
Bituminous membranesFactory-made sheet of consistent thicknessTight laps, sealed edges, and protection before backfillSelected according to the specification in the drawings
Crystalline materialsCrystals block the pores of the concreteDamp surface with no standing water, and wet curing after applicationThe Penetron data sheet calls for keeping the surface damp for five days
Figures are attributed to the manufacturers' data sheets listed in the sources. Always follow the data sheet of the actual product used on your site.

In ordinary dry soil, a rubberised bitumen coating in two coats with good protection is often enough. Where the groundwater table is close or the soil is saline, the designer specifies a stronger system, which may combine more than one material.

Does the waterproofing need protection before backfill?

Yes, and it is the step most often skipped. Backfilling is a rough process: stones slide down the sides, a loader pushes soil, and a compactor vibrates against the wall. A film about a millimetre thick will not survive that without something covering it.

Fosroc describes its protection boards as rot-proof, bitumen-impregnated boards intended to protect waterproofing membranes from mechanical damage. Common alternatives are polystyrene boards or a thin mortar layer on the top face of the tie beam, depending on what the engineer approves.

Before you allow backfilling, confirm that

  • Every buried face is covered, with no gaps at corners or necks
  • There are no blisters, bulges or visibly thin areas
  • The drying time stated on the product data sheet has passed
  • Protection boards are fixed and cover the side faces
  • Drainage and supply pipes passing through the beam are sealed around
  • Backfill soil is clean, free of debris and large stones
  • You photographed every face before it was covered, for future reference

Printable checklist — use your browser's print command.

What mistakes ruin foundation waterproofing before backfill?

  • Sealing the sides and forgetting the top of the tie beam: that is exactly the face that touches the wall blocks and passes moisture into them.
  • One thick coat instead of two: a single coat leaves pinholes, and the second coat closes them.
  • Backfilling the same day: soft coating sticks to the soil and peels off during compaction.
  • Backfilling with construction waste: broken block and rebar offcuts tear the film and trap water around the foundation.
  • Waterproofing over untreated honeycombing: the film bridges the void for a while, then punctures under soil pressure.
  • Ignoring pipe penetrations: any pipe through the beam without sealing around it becomes a channel for water.

Who specifies the waterproofing system and who inspects it?

The design engineering office specifies the system based on the soil report, the contractor carries it out, and the supervising engineer signs it off before backfill. If your drawings do not state the waterproofing type and number of coats, ask the office to confirm them in writing before work starts. Any major honeycombing or cracking in the footings should be shown to a licensed structural engineer before it is covered.

Our team at Azl carries out foundation waterproofing to the specification in your drawings and hands over each stage with photos before backfill. You can request an inspection a few days before the backfill date so the site is not delayed.

Frequently asked questions

Is one coat of bitumen on the footings enough?

It is not recommended. Most data sheets for bitumen emulsions call for at least two coats, because the first coat contains tiny pinholes and air bubbles that the second coat closes. The required thickness is also rarely reached in one coat without the material running down vertical surfaces.

How long should I wait after waterproofing before backfilling?

The reference is the data sheet of the product used and the site conditions. Water-based coatings take longer in humid or cool weather and less in summer. As a practical rule, do not backfill until the coating is fully dry and protection is fitted over it, and have the supervising engineer confirm this at handover.

Should the top face of the tie beam also be waterproofed?

Yes. The top face is the surface on which the ground-floor blocks are laid, and if it is left bare, rising ground moisture passes through the concrete into the wall. Many cases of damp at the base of walls come from neglecting this one face.

Does crystalline waterproofing replace bitumen coating?

It depends on the design. Crystalline materials work inside the pores of the concrete and, according to their manufacturers' data sheets, resist water pressure, but they do not bridge large moving cracks. Some designers use them alone and others combine them with an outer membrane. The decision belongs to the engineering office based on the soil report.

What should I do if the foundations were backfilled without waterproofing?

Do not ignore it. Ask a structural engineer or engineering office to assess the soil aggressiveness and groundwater level. The fix may be partial excavation and waterproofing from outside, or treatment from inside at wall level. The decision depends on the site condition, not on a general rule.

Ask an engineer about your case

Write your question about this topic, and an Azl specialist will reply during working hours.

Topic: Waterproofing Foundations Before Backfilling: Steps From Formwork Removal to the First Soil Layer

Nothing is stored on this website; your message opens in WhatsApp for you to send to 0544027180. Privacy policy

References and sources

  1. Sika Igolflex AE Product Data Sheet — Sika Gulf · gcc.sika.com
  2. Protection Board — Fosroc · fosroc.com
  3. Nitoproof 21 - Waterproofing bitumen emulsion — Fosroc · fosroc-online.com
  4. PENETRON Data Sheet — The Penetron Group · penetron.com
  5. اشتراطات إنشاء المباني السكنية 1446هـ / 2024م — وزارة الشؤون البلدية والقروية والإسكان · momah.gov.sa

External links pass through Azl's Consumer Safety Center for checking before leading to other organisations' websites. Citing them does not imply they endorse Azl. Technical values are typical and vary by product; the final reference is the approved product's datasheet and the project design. Editorial policy