Epoxy Floor Installation Steps, With the Waiting Times From the Data Sheets

Updated: 8 min readBy the Azl technical teamEpoxy flooring

Installing a glossy grey epoxy floor in a warehouse with a spiked de-aerating roller
Installing a glossy grey epoxy floor in a warehouse with a spiked de-aerating roller — Illustrative image

Epoxy work looks simple from the outside: mix two components and spread them on the floor. But most of what decides the life of the floor happens before the tins are opened, and what happens afterwards is governed by hours and minutes set by the product's technical data sheet, not by the installer's mood.

Here we set out the installation steps as they should be carried out, using the figures published in the Sikafloor-264 (roller system) and Sikafloor-263 SL (self-levelling system) data sheets as two documented examples. Every other product has its own numbers, and the rule is constant: the data sheet is the reference.

What is checked before epoxy floor installation begins?

Before any grinding, the concrete and the weather are judged. Both data sheets require concrete moisture below 4% by weight and a surface tensile strength of at least 1.5 N/mm². ASTM D4263 sets out a plastic sheet test as an indicator of capillary moisture in concrete that could harm coatings that do not tolerate moisture; it is a preliminary check and does not replace measurement with an instrument.

Application conditions in the data sheets
ConditionSikafloor-264Sikafloor-263 SL
Air temperature+10 to +35°C+10 to +30°C
Relative humidity80% maximumAs per the data sheet
Surface temperatureAt least 3°C above dew pointWithin the same air temperature limits
Concrete moistureBelow 4% by weightBelow 4% by weight and no rising damp
Surface tensile strengthAt least 1.5 N/mm²At least 1.5 N/mm²
Source: the technical data sheets of the two products. In the Saudi summer the temperature limit means working at night or dawn in spaces without air conditioning.

How is the concrete prepared before epoxy installation?

Epoxy bonds to the surface, not to the sound concrete beneath, so if there is weak cement laitance, old paint or oil on the surface, it will come away with it. All of that is therefore removed mechanically. The concrete surface profile guide based on ICRI's method shows that thin coatings need a low profile (CSP 1 to 2), high-build coatings CSP 2 to 3, and self-levelling systems CSP 3 to 6, and that mechanical abrasion is the first and safest option.

  1. 1

    Clear the space and protect surroundings

    Remove furniture, protect the bottom of walls and doors, and close the space to traffic for the whole duration of the work.

  2. 2

    Grinding or shot blasting

    Diamond grinding or shot blasting to the profile the system requires, with dust extraction during the work.

  3. 3

    Repair

    Fill stable cracks and holes with epoxy putty or mortar, and treat expansion joints so that they keep their ability to move.

  4. 4

    Final vacuuming

    A thorough industrial vacuum, because fine dust left behind forms a separating layer between the concrete and the primer.

Details of repair materials and which suit each defect are in the guide to epoxy putty.

Primer and mixing: where do the minutes go?

The primer soaks into the pores of the concrete, seals them and forms the bridge between the concrete and the coats that follow. Euclid Chemical recommends applying coatings while the concrete temperature is falling, not rising, because rising temperature pushes air out of the pores and creates bubbles and pinholes. In practice that means starting in the late afternoon or evening.

Once the two components are mixed, a countdown begins. The Sikafloor-264 data sheet gives a pot life of about 45 minutes at 10°C, 20 minutes at 20°C and 12 minutes at 30°C. For Sikafloor-263 SL it is about 60, 30 and 15 minutes respectively. Mixed material left in the bucket heats up and hardens faster, so it is spread on the floor as soon as it is mixed.

Mixing rules

  • Mix the whole pack in the ratio set by the manufacturer, with no arbitrary splitting.
  • Use an electric mixer at low speed until the colour is uniform and no streaks remain.
  • Do not add water or solvent to make spreading easier unless the data sheet says so.
  • Mix batches of a size that can be spread before pot life ends, especially in heat.

Printable checklist — use your browser's print command.

Applying the main coats and the recoat window

For the roller system, the Sikafloor-264 data sheet gives consumption of about 0.25 to 0.3 kg/m² per coat, normally two coats. For the thicker self-flowing layer of the same product it is about 0.9 to 1.2 kg/m². Sikafloor-263 SL is applied at a thickness between 1 and 6 mm, with consumption of about 1.6 to 2.0 kg/m² per millimetre depending on the filler ratio. In usual practice the self-levelling layer is spread with a notched trowel, then a spiked roller is passed over it to release trapped air.

Between coats there is a time window with a minimum and a maximum. Before the minimum the coat is still soft, and after the maximum it becomes hard and smooth so the next coat will not bond to it without abrading it first.

Recoat window for Sikafloor-263 SL
Surface temperatureMinimum waitMaximum wait
+10°C30 hours3 days
+20°C24 hours2 days
+30°C16 hours1 day
For Sikafloor-264 itself at 20°C: 24 hours minimum and 2 days maximum.

If the air is humid or the temperature falls at night, a waxy, greasy film called "amine blush" may form on the surface. Carboline explains that it results from moisture and carbon dioxide reacting with the epoxy hardener, that it may be invisible or show as a colour change, and that it must be washed off and removed before any later coat or bonding suffers. This is common in coastal cities such as Jeddah and Dammam.

Anti-slip and the top coat

On ramps and washing areas, quartz sand is broadcast onto the coat while it is wet and then sealed with a top coat, and both data sheets state that a slip-resistant surface can be obtained. In spaces that receive sunlight, a UV-resistant top coat is preferred, because both data sheets note that direct sunlight may change the colour of epoxy without affecting its performance.

When can you walk on the floor and use it fully?

Readiness of the floor for use after the last coat
UseSikafloor-264 at 20°CSikafloor-263 SL by temperature
WalkingAbout 24 hoursAbout 18 to 72 hours
Light trafficAbout 4 daysAbout 2 to 6 days
Full cureAbout 7 daysAbout 5 to 10 days
Higher temperature shortens the times and lower temperature lengthens them. Follow the data sheet of the product actually used.

During these days ventilation stays on, and washing the floor, placing heavy furniture or dragging anything across it is not allowed. Details on smell and when occupants can return are in epoxy odour and occupant safety, and general safety guidance is on the health and safety page.

Common epoxy shortcuts that ruin the result

  • Acid-washing the floor instead of grinding it, to save time.
  • Skipping the moisture test on ground floors because the floor "looks dry".
  • Applying at midday in an unconditioned space, exceeding the temperature limit in the data sheet.
  • Passing the maximum recoat window without abrading the previous coat.
  • Opening the space to use after one day because the surface is "dry" to the touch.

Each of these shortcuts has a known effect, and you can see how to read their traces in causes of epoxy floor peeling. For the material's general properties see the epoxy guide. If you want an installation that documents each step from testing to handover, request an inspection through Azl's epoxy flooring service.

Frequently asked questions

How many days does an epoxy floor installation take?

Preparation and repair take a day or more depending on area and condition, then each coat needs a wait before the next; the Sikafloor-264 data sheet gives 24 hours minimum at 20°C. After the last coat you can walk after about a day and reach full cure after about 7 days. So plan one to two weeks overall.

Can epoxy be installed without grinding the floor?

It is not recommended. A concrete surface often carries weak cement laitance or residues that prevent bonding. The ICRI surface profile guide shows that each coating needs a specific profile and that mechanical abrasion is the first option. Applying without grinding is one of the best-known causes of early peeling.

What is the best time to install epoxy in summer?

Evening and dawn in spaces without air conditioning. The Sikafloor-264 data sheet sets air temperature between +10 and +35°C, and the Sikafloor-263 SL sheet a maximum of +30°C, and pot life shortens sharply in heat. Euclid Chemical also recommends applying while temperature is falling to reduce bubbles.

What happens if the second coat is late?

If the maximum recoat window is exceeded, the first coat becomes hard and smooth and the next coat does not bond well, so it must be lightly abraded and cleaned before continuing. For Sikafloor-263 SL, for example, the maximum is 2 days at 20°C and only 1 day at 30°C.

What is the greasy film that sometimes appears on epoxy?

Usually amine blush, a waxy film that, as Carboline explains, results from moisture and carbon dioxide reacting with the epoxy hardener in humid or cool conditions. It does not harm the coat itself but prevents anything above it from bonding, so it is washed off and removed before any later coat is applied.

Ask an engineer about your case

Write your question about this topic, and an Azl specialist will reply during working hours.

Topic: Epoxy Floor Installation Steps, With the Waiting Times From the Data Sheets

Nothing is stored on this website; your message opens in WhatsApp for you to send to 0544027180. Privacy policy

References and sources

  1. Sikafloor-264 Product Data Sheet — Sika · industry.sika.com
  2. Sikafloor-263 SL Product Data Sheet — Sika GCC · gcc.sika.com
  3. ASTM D4263 Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method — ASTM International · store.astm.org
  4. Concrete Surface Profiles (ICRI CSP method selector) — TCC Materials · tccmaterials.com
  5. How to Prevent Coating Defects Caused by Concrete Outgassing — Euclid Chemical · euclidchemical.com
  6. Amine blushing: identification, prevention and remediation — Carboline · carboline.com

External links pass through Azl's Consumer Safety Center for checking before leading to other organisations' websites. Citing them does not imply they endorse Azl. Technical values are typical and vary by product; the final reference is the approved product's datasheet and the project design. Editorial policy